公告單位  營繕組  公告日期  2026/4/8
 主  旨  【停電公告】建國校區高壓開關設備更新及新變壓器線路裝設停電工程Power Outage Announcement: High-voltage switchgear upgrade and new transformer line installation at Jianguo Campus.
 內  容 
一、停電原因:進行建國校區高壓開關設備更新及新變壓器線路裝設工程 開關設備更換,須停電施作。
二、施工日期:115年5月1日(五)上午8:00~22:00。
三、施工地點:智慧樓地下室電氣室機房。
四、停電時間及範圍:
(一)上午8:00~10:00 協力樓及智耕樓、圖書館全館。早上10:00後供電。
(二)上午8:00~22:00 教學區智慧樓A棟、精進樓B.D.E棟、圖書館C棟。晚上22:00後供電。
五、注意事項:停電期間飲水機暫停使用,若工程提早完成送電則不另行通知。
六、施工期間非工程人員請勿進入工程管制範圍以免發生危險,造成不便之處,敬請見諒。
※若有任何疑問,請預先通知營繕組#22358吳榮源先生、#22309周宜靜小姐。

總務處營繕組敬啟

**Notice Regarding Scheduled Power Outage for Infrastructure Upgrades**

**1. Reason for Outage:**
The power outage is necessary to facilitate the replacement of high-voltage switchgear and the installation of new transformer lines at the Jianguo Campus. The switchgear replacement requires a temporary power shutdown.

**2. Construction Period:**
May 1, 2026 (Monday), from 8:00 AM to 10:00 PM.

**3. Construction Location:**
Electrical Room in the Basement of the Zhi Hui Building.

**4. Scheduled Outage Times and Affected Areas:**
- (1) 8:00 AM to 10:00 AM: Xie Li Building, Zhi Geng Building, and the entire Library. Power will be restored after 10:00 AM.
- (2) 8:00 AM to 10:00 PM: Zhi Hui Building (A Wing), Jing Jin Building (B, D, E Wings), and Library (C Wing). Power will be restored after 10:00 PM.

**5. Important Notes:**
During the outage, drinking water dispensers will be temporarily unavailable. If the work is completed earlier than scheduled and power is restored, no further notice will be given.

**6. Safety Precautions:**
Non-authorized personnel are strictly prohibited from entering the construction area during the work period to avoid any potential hazards. We apologize for any inconvenience caused.

※For any inquiries, please contact Mr. Wu Rong-Yuan, tel. #22358, or Ms. Chou Yi-Ching, tel. #22309, of the Maintenance Section.

Warm regards,

Construction and Maintenance Group