一、施工事項:中央校區教學區燈具更新工程(施工區域:勤耕樓)。
二、施工日期:115年3月16日(週一)至115年3月21日(週六)。
三、施工時間:8:00至17:00。
四、施工地點:中央校區教學區勤耕樓使用舊式T5、T8燈具之房間(詳如附件-施工計劃表)。
五、配合事項:本工程因配合「經濟部商業服務業節能補助」申請,需於學期中施工,施工期間會有少許噪音及灰塵,且照明燈具會暫時關閉,請各單位教職員生配合廠商現場施作,不便之處,敬請見諒。
六、附註說明:
1.本工程會將原有舊式T5、T8燈具更新為新式LED節能燈具,燈具亮度會有差異,需有一段適應期。
2.若因有排課或活動,無法配合排定之施工日期,請事先與營繕組聯絡。
3.若有任何疑問,請聯絡營繕組陸偉民、陳月霞,分機:11315、11314。
總務處營繕組敬啟 **Notice Regarding Lighting Upgrade Project at Central Campus Teaching Area**
**I. Project Details:**
Lighting Upgrade Project at Central Campus Teaching Area (Construction Site: Qin Geng Building).
**II. Construction Period:**
From Monday, March 16, 115 to Saturday, March 21, 115.
**III. Construction Hours:**
8:00 AM to 5:00 PM.
**IV. Construction Location:**
Rooms within the Central Campus Teaching Area is Qin Geng Building that currently use outdated T5 and T8 lighting fixtures (see attached Construction Plan for details).
**V. Matters for Cooperation:**
This project is conducted to comply with the application requirements for the "Energy-Saving Subsidy for Commercial Services" provided by the Ministry of Economic Affairs. As a result, construction must take place during the semester. During the construction period, there will be some noise and dust, and the lighting fixtures will be temporarily turned off. All faculty, staff, and students are kindly requested to cooperate with the on-site work of the contractor. We apologize for any inconvenience caused.
**VI. Additional Notes:**
1. The outdated T5 and T8 lighting fixtures will be replaced with new LED energy-saving fixtures. There may be differences in brightness, and an adaptation period is expected.
2. If any unit has scheduled classes or activities that conflict with the planned construction dates, please contact the Construction and Maintenance Section in advance.
3. For any inquiries, please contact Lu Wei-Min or Chen Yue-Xia at the Construction and Maintenance Section, extension numbers 11315 and 11314, respectively.
Warm regards,
Construction and Maintenance Group |
|