內 容
|
一、停電原因:台電公司巡檢本校中央校區教學區高壓電供電設備,發現保開關機構異常無法正常操作及絕緣氣體(SF6)不足之情形,為避免設備故障而影響本校供電安全,需停電施作設備更換工程。
二、施工日期:113年10月26日(星期六)08:00至12:00。
三、停電範圍:和敬樓、勤耕樓、大捨樓、福田樓、大愛樓與大喜館全區。
四、停電注意事項:
(一)施工期間將不供應台電電源,僅供應緊急發電機電源(紅色插座電源及緊急電源迴路照明)。
(二)為節約能源,大喜館發電機將不啟動,故施工期間全館停電。
(三)請各單位於以上施工日期內,請勿安排各類活動或課程,以免受到停電影響。
(四)各單位之用電設備,無設置穏壓設備者,停電期間請勿開啟運轉或可將插頭拔取,以避免設備故障或異常。
(五)各單位管理之空間,如設置有重要設備或不可斷電之儀器者,請派員到校監督設備送電後是否正常運作,以避免財產損失或遭受影響。
(六)保養作業完成後,總務處營繕組會進行送電,並檢視公共區相關分電站或電氣室是否正常供電,各單位如有停電情形,請通知本組處理完成復電,造成不便,敬請見諒。
※若有任何疑問,請預先通知營繕組11314陳月霞小姐或11315陸偉民先生。
總務處營繕組 敬啟
[Power Outage Announcement] Announcement on the construction of high-voltage electrical equipment in the main campus teaching area
1.Reason for Power Outage: During an inspection of the high-voltage power supply equipment in the main campus teaching area of the university's central campus, Taiwan Power Company discovered an abnormality in the circuit breaker mechanism, which could not operate properly, as well as insufficient insulation gas (SF6). To prevent equipment failure and ensure the safety of the university’s power supply, a power outage is required for equipment replacement work.
2.Maintenance Dates: The maintenance is scheduled for October 26, 2024 (Saturday), from 8:00 AM to 12:00 PM.
3.Areas Impacted: The outage will affect He-Jing Building, Qin-Geng Building, Da-She Building, Fu-Tian Building, Da-Ai Building, and the Sports Center.
4.Important Information During Maintenance:
(a)Emergency Power: Only emergency power sources will be available, including red socket outlets and emergency circuit lighting.
(b)Power in the Sports Center: The Sports Center generator will be offline to save energy. As a result, there will be no power in the entire facility during the maintenance period.
(c) Please refrain from scheduling any activities or classes during the aforementioned construction dates to avoid being affected by the power outage.
(d)Equipment Use: to avoid damage or malfunction, devices lacking voltage stabilizers should not be used or plugged in during the outage.
(e)Supervision of Critical Equipment: Units overseeing areas with vital or uninterruptible power equipment should closely monitor these devices to ensure their proper operation after maintenance.
(f)Power Restoration: Post-maintenance, the Construction and Maintenance Group will restore power and verify that all substations and electrical systems in public areas are operational. Any post-restoration power issues should be promptly reported for resolution.
For any inquiries, please contact Ms. Yueh-Shia Chen at (03)856-5301, Ext. 11314, or Mr. Wei-Min Lu at the same number, Ext. 11315.
We sincerely apologize for any inconvenience this may cause and greatly appreciate your understanding and cooperation.
Warm regards,
Construction and Maintenance Group
|
|